- Location
- Greater Toronto Area
- Completed
- September 2026
The problem
A landing is where every visitor steps, and it is where a weak base shows first. This one had settled. A landing that settles becomes a trip hazard, and it holds water against the step in winter.
The repair
The pavers were sound, so nothing was thrown out. They were lifted and stacked, the base underneath was re-graded and compacted, and the same pavers went back down to a level line between the concrete borders. The second photo shows the landing mid-repair, with the base exposed.
This is the usual answer for sunken interlock: fix what is underneath and re-use what is on top. It costs a fraction of replacement.
What we built
- ✓Pavers lifted and stacked for re-use
- ✓Base re-graded and compacted
- ✓Same pavers re-laid level between the concrete borders, joints re-sanded
Photos from this job